We propose a small data center on East Strand, starting with 4.8 MW of computing (IT load). 42 MW of computing is about 48 MW of total load. We would cap the site under 50 MW.
It would offer heat for glasshouses and buildings, backup power and heat for the City's wastewater plant, a public creek walk and raised flood edge, and a community charge of $5 per contracted kW per month.
It would run on natural gas fuel cells, which emit more carbon per unit of power than the upstate grid average (Power and carbon shows the numbers).
It is not approved, financed or built, and there is no site control.