These answers explain what we propose and what remains unknown. Send other questions or criticism through workload.net.
GasWould it use gas?

Proposed: fuel cells alone would provide base generation, without combustion stacks. We would also study grid supply. Natural gas is a fossil fuel.

Bloom's manufacturer paper gives 679 to 833 lb CO2/MWh for gas fuel cells, without describing a selected supplier. EPA eGRID 2023 gives a historical upstate grid average of 241 lb CO2/MWh. We make no clean or carbon-neutral claim.

We would publish full emissions, including methane, and a path toward lower-carbon supply. State climate law and air permits could limit gas options; counsel would need to check legal thresholds.

GasDoes Central Hudson supply the project?

No request has been made and no agreement exists. Being near a gas facility establishes no available capacity.

WaterWill it use drinking water for cooling?

No. The cooling loops would be filled once and sealed. Each hall would have full-load independent closed-loop cooling. No creek withdrawal or discharge is planned. Water use would be metered and published.

WaterWill sewage be used on crops?

No sewage would touch crops. Treated effluent could exchange heat through isolated heat exchangers only, separate from food systems.

NoiseWill it be noisy?

Proposed: sound would stay at or below 55 dBA at night at the nearest homes (City of Kingston Code, Chapter 300, section 300-6: 55 dBA at residential boundaries from 10 pm to 7 am). Enclosures and a public sound monitor would be required.

No sound performance has been measured.

TaxesWill it pay taxes?

Proposed: the project would pay full property tax on the compute and would not seek a property tax abatement for the data halls.

FloodHow would it handle flooding?

FEMA maps parts of the Rondout as flood hazard areas. We propose modular natural gas fuel cells immediately next door to Central Hudson's existing regulator parcel at East Strand's eastern end. Separate batteries (BESS) and electrical distribution would sit on flood-resilient platforms. Utility capacity, environmental review, setbacks, and permits would decide whether this could proceed. No adjoining parcel is identified as a project site. Halls would extend westward only where land depth, setbacks, and permits allowed. Platforms would raise equipment above design flood elevation.

Waterfront buildings would use pile platforms with floodable space underneath. The promenade could help defend the waterfront, subject to hydraulic engineering and no-rise approvals.

PowerWill it raise local electricity prices or strain the grid?

Any grid connection would need Central Hudson studies and Public Service Commission review. We would aim to provide our own reliable supply and batteries without burdening local customers, subject to those processes.

EmissionsWhat about local air quality?

Fuel cells make electricity without burning the gas, so local NOx and particulates would be very low. They would still emit CO2. NYSDEC would decide what air permits apply. We would publish monitoring results.

AccessWill the waterfront be private?

We propose a continuous public creek walk, open year-round.

AccessHow would people get there?

We propose a free electric trolley between Uptown and the waterfront. It would start with weekend and event service, and run with the county transit system if it agreed. Parking on the strip would be limited to drop-off and access.

BenefitsWhat does Kingston get?

Proposed: a $5 per contracted kW per month community charge would be paid before investor distributions. Cultural tenants would pay no fixed base rent, with modest percentage rent and capped total occupancy cost. Studios and galleries would pay a lower share.

The charge would help with fit-out, community compute credits, and a public waterfront. None of this is guaranteed today.

ScaleHow big would it get?

We propose a pilot with 4.8 MW of computing (IT load), then a 9.6 MW first node. Later 16.8, 24, or 42 MW IT steps would be conditional. The 42 MW study ceiling carries no approval or binding commitment.

42 MW of computing is about 48 MW of total load. We would cap the site under 50 MW.

HousingHow many homes?

No number is proposed. Housing would be modest and partner-led on the hillside across East Strand.

StatusIs this happening?

It is a proposal. Nothing is operating, approved, financed, or under contract. We are asking for comments before taking it further.

Carbon sources: Bloom Energy manufacturer white paper and EPA eGRID 2023 summary data.